09/03/2024
Here the Antaris 5.5 with the repeller D4.40m on a 9.20m tilting mast.
The Antaris is working here in 3-phase parallel to the grid with the TRIO 5.8 from FIMER.
Our customer fought valiantly for 1.5 years for his planning permission.
And yes, almost to the day, with the commissioning of the wind turbine, small wind turbines are now also exempt from planning permission in SH up to a total height of 15 metres.
But one consolation remains: a soil survey was carried out for the foundations. It turned out that the required soil pressure was not sufficient and the foundation size had to be adjusted.
Therefore, our advice to all future ‘ANTARIS windmillers’ is to always have the ground checked if the ground conditions are unclear.
This can also be done by the local civil engineer if necessary!
If you have any questions about the project, please contact us, we will be happy to advise you.
Enjoy the wind with Antaris wind turbines!